Phase 1
January 2018 - February 2018
Phase 2
February 2018 – June 2019
RFP Development & Vendor Selection
RFP Creation and Issuance: Mission Broadband drafted and released RFPs for the design, construction, and operation of the island’s broadband network.
Vendor Evaluation: Responses were rigorously reviewed based on technical merit, design quality, project management capabilities, and cost efficiency.
Strategic Partner Selection: The most qualified vendors were recommended to the town, laying the foundation for successful network construction and service delivery.
Phase 3
June 2019 – April 2024
Island-Wide FTTP Network Buildout
Community Engagement: Surveys and public forums were conducted to gather feedback and maintain transparency throughout the project.
Infrastructure Mapping and Design: A comprehensive inventory of poles and underground facilities was developed, leading to a detailed FTTP network design.
Vendor Coordination and Network Deployment: Vendors were officially selected, and Mission Broadband stayed on in the role of Operations Oversight to manage the buildout of 53 miles of fiber optic cable, leveraging subsea fiber for scalable, high-speed connectivity.